Sungi’s river flood control infrastructure development project has a high enough risk. The research objective is to identify, assess, and respond to the risks that affect the cost and time performance of the project. The study was conducted by a mixture of quantitative descriptive and qualitative descriptive methods. Data collection by interview and data analysis by Severity Index (SI). The results showed that the identified risks were 25 (twenty-five) risks from 8 (eight) sources of risk. Risks that have extreme value and affect cost performance are addendums when carrying out work, changing or erratic weather that hinders work and adjustments to field conditions resulting in work design changes. Risks that have extreme values ​​and affect the performance of time are a lack of funding to carry out work and an error in field measurements to determine the point of work so it does not match the picture. The response to risks includes service providers providing initial funding, implementing addendums immediately, using weather forecast data from the BMKG, re-measuring, and making changes immediately, and asking for the approval of the work owner. 

References

Anonim., (2015), Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 28 Tahun 2015 tentang Penetapan Garis Sempadan Sungai dan Garis Sempadan Danau, Jakarta, pp. 3

Anwar., (2014), Analisa Resiko Teknis yang Mempengaruhi Kinerja Waktu Proyek Pembangunan Pengaman Pantai di Provinsi Sulawesi Barat, Magister Tesis, Institut Teknologi Sepuluh Nopember, Surabaya.

Asmarantaka, N.S., (2014), Analisis Resiko yang Berpengaruh Terhadap Kinerja Proyek pada Pembangunan Hotel Batiqa Palembang, Jurnal Teknik Sipil dan Lingkungan, 2(3), pp. 483-491.

Azhari., Aulia, T.B., Madjid, I.A., (2014), Faktor – Faktor Risiko yang Mempengaruhi Kinerja Kontraktor pada Pelaksanaan Proyek Infrastruktur di Kabupaten Aceh Jaya, Jurnal Teknik Sipil, 3(1), pp. 1-14.

Darmawi, H., (2016), Manajemen Risiko, 2th, Bumi Aksara, Jakarta, pp. 20-23

Dewi, E.L., Pratama, I.A., (2013), Analisis Risiko pada Pekerjaan Pengamanan Pantai Klating di Kabupaten Tabanan, Media Bina Ilmiah, 7(1), pp. 64-68.

Honesti, L., Salpani., Djali, N., (2011), Identifikasi Faktor-Faktor Resiko yang Mempengaruhi Kinerja Biaya pada Proyek Irigasi di Kabupaten Kerinci, Jurnal Teknik Sipil Universitas Bung Hatta, 5(3), pp. 13-23.

Mahadipta, N.G.D., (2010), Analisis Risiko pada Proyek Pembangunan Sentral Parkir di Pasar Badung, Magister Tesis, Universitas Udayana, Denpasar.

Maliki, I.N., (2016), Evaluasi Faktor-Faktor Dominan Risiko Teknis Pelaksanaan Proyek Jember Icon Tahap Dua dengan Metode Severity Index, Strata 1 Skripsi, Universitas Jember, Jawa Timur.

Nizamuddin., Masimin., Madjid, I.A., (2013), Faktor-Faktor Risiko yang Mempengaruhi Kinerja Tahap Pelaksanaan Proyek Irigasi (Studi Kasus Di Provinsi Aceh), Jurnal Teknik Sipil, 2(1), pp. 12-25.

Norken, I.N., Purbawijaya, I.B.N., Suputra, I.G.N.O., (2015), Pengantar Analisis dan Manajemen Risiko pada Proyek Konstruksi, Udayana University Press, Denpasar, pp. 9

Pratama, I.A., (2014), Identifikasi Risiko pada Pelaksanaan Proyek Pembangunan Dermaga/ Pelabuhan di Nusa Penida, Media Bina Ilmiah, 8(1), pp. 24-29.
Published
2020-10-15