ANALISIS PROBABILITAS KETEPATAN BIAYA DAN WAKTU MENGGUNAKAN KONSEP NILAI HASIL DAN MONTE CARLO

  • Putri Ayu Mentari Program Studi Teknik Sipil Fakultas Teknik Universitas Mercu Buana
  • Mirnayani . Program Studi Teknik Sipil Fakultas Teknik Universitas Mercu Buana
Keywords: Project delays, Earned Value Method, Monte Carlo Simulation, Construction Project

Abstract

The SIBS Women's Dormitory Building Construction Project faced significant delays and design alterations, causing changes in project costs and timelines. This study aims to identify delay factors, evaluate cost and time performance using the Earned Value Method (EVM), and estimate the probability accuracy of cost and duration using Monte Carlo simulation. Data were collected through direct observations, stakeholder interviews, and document analysis. Main factors causing delays include adverse weather, challenging site accessibility, delayed material deliveries, and a design change from three to four floors. Initial completion estimates of 623 days showed an accuracy probability of 2.03%, while the revised EVM estimate of 652 days significantly improved accuracy to 73.91%. The probability accuracy for remaining costs of Rp1.948.950.796 using EVM was 19.61%. The findings suggest combining EVM with Monte Carlo simulation effectively enhances predictions and management of construction project costs and durations.

References

Afiq, M. (2021). Manajemen Risiko Pada Proyek Pembangunan Gedung Asrama Mahasiswa Uin Walisongo Tahun 2021. 3(1).
Ahadian, E. R. (2022). Penyebab Keterlambatan Pekerjaan Pada Proyek Konstruksi Di Kota Ternate. Jurnal Sipil Sains, 12(2).
Alkas, M. J., Sari, D. P., Haryanto, B., & Ramadanri, N. A. (2023). Pengendalian Biaya Dan Waktu Proyek Dengan Metode Analisis Nilai Hasil Menggunakan Microsoft Project. 1(1), 8–15.
Boy, W., Erlindo, R., & Fitrah, R. A. (2021). Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Gedung Kuliah Pada Masa Pandemi Covid 19. Jurnal Rivet, 1(01), 57–64.
Deng, J., & Jian, W. (2022). Estimating Construction Project Duration and Costs upon Completion Using Monte Carlo Simulations and Improved Earned Value Management. Buildings, 12(12), 2173.
Dewaji, M. R., Utomo, C., & Supani, S. (2023). Analisis Kinerja Waktu Dan Biaya Proyek Revitalisasi RCC RU VI Balongan Dengan Metode Probabilistic Earned Value. Jurnal Teknik Its, 12(1).
Erviani, R. N. D., & Nurcahyo, C. B. (2023). Analisis Penjadwalan Proyek Pembangunan Gudang Marunda Menggunakan Simulasi Monte Carlo. Jurnal Teknik Its, 12(2).
Henong, S. B. (2022). Dampak Pandemi Covid-19 Terhadap Penyelesaian Proyek Konstruksi: Tinjauan Literatur Sistematis. Journal of Sustainable Construction, 2(1), 23–29.
Kendek, A. T. M., & Rachmawati, F. (2024). Analisis Penjadwalan Probabilistik (Studi Kasus: Proyek Apartemen Grand Shamaya Tower Aubrey). Jurnal Teknik Its, 13(1).
Mirnayani, M., Vidayanti, D., & Susanti, I. I. (2025). Simulasi Model Risiko Pekerjaan Perbaikan Tanah Metode Konsolidasi Berbasis Value Engineering. Jurnal Ilmiah MITSU (Media Informasi Teknik Sipil Universitas Wiraraja), 13(1), 105–118.
Moerdiwanto, M. F., & Zuhdy, A. Y. (2023). Analisa Perhitungan Waktu Dan Biaya Pada Proyek Pembangunan Gedung DPRD Balai Pemuda Surabaya Dengan Metode Earned Value Management. Jurnal Teknik Its, 12(1).
Perdana, M. S. A., & Sari, R. P. (2022). Optimalisasi Waktu Pelaksanaan Proyek Konstruksi Rumah Tinggal Menggunakan Metode CPM (Critical Path Method) Dan PERT (Program Evaluation and Review Technique). Jurnal Media Teknik Dan Sistem Industri, 6(2), 116.
Setyabudi, P. W., & Mirnayani. (2023). Analisis Kinerja Biaya Dan Waktu Dengan Konsep Earned Value Analysis Pada Masa Pandemi Covid-19 (Studi Kasus Proyek Pabrik Manufacture Automotive di Kawasan Industri Mitra Karawang Timur). Jurnal Teknik Sipil, 4(2), 543–550.
Sigit, A. (2019). Evaluasi Biaya Dan Waktu Pada Proyek Penggantian Jembatan Dengan Menggunakan Metode Konsep Nilai Hasil. Teknisia, XXIV(2), 117–125.
Sofia, D. A., Wildan, M., & Yusdinar, H. (2022). Analisis Kinerja Proyek Pembangunan Gedung Menggunakan Konsep Earned Value. 4(1).
Wijaya, F. S., & Sulistio, H. (2019). Penerapan Metode Monte Carlo Pada Penjadwalan Proyek Serpong Garden Apartment. JMTS Jurnal Mitra Teknik Sipil, 2(3), 189.
Published
2026-04-30
Abstract viewed = 0 times
PDF (Bahasa Indonesia) downloaded = 0 times