ANALISIS MANAJEMEN PROYEK PEMBANGUNAN RUMAH SUSUN LANJUTAN DI DESA KENTEN LAUT PROVINSI SUMATERA SELATAN
Abstract
In the implementation of the construction of a construction project, there are three main things, namely cost, quality and time, which are interrelated, where a project can be completed on time with minimal costs and of good quality. In today's technological developments, especially in construction engineering management, to assist the work, many applications have been made in the completion of construction project engineering management. One of them is the Microsoft Project 2010 application, which can simplify the planning and implementation of a project schedule. The construction of advanced flats in Kenten Laut Village, South Sumatra Province, in the 18th week has experienced a time delay of 26% which should have reached 36% progress schedule, but the realization is only 10%. This is due to obstacles during the construction of the ground floor structure (foundation work). To speed up the work time, a re-planning of work productivity and work duration was carried out with the Microsoft Project 2010 application. From the re-planning of the advanced flat construction project in the village of Kenten Laut, South Sumatra province, structural work which includes columns, beams and floor slabs can be accelerated with a duration of work from 168 days to 132 days.
References
Amiwarti,A.,& Serlika, J (2018). Analisis Proyek Pembangunan Gedung Asrama Mahasiswa Universitas PGRI Palembang, Jurnal Deformasi, 3(1). 19-26
Bakhtiyar, A., Soehardjono, A., & Hasyim, M. H. (2012). Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota Lamongan. Rekayasa Sipil, 6(1), 55-66.
Deshariyanto, D. (2013). Faktor-faktor yang Mempengaruhi Waktu Pelaksanaan Proyek Konstruksi di PU. Bina Marga Kabupaten Sumenep. Jurnal Ilmiah MITSU, 1(2).
Ervianto, W. I. (2004). Teori-aplikasi manajemen proyek konstruksi. Yogyakarta : Andi
Fansuri, S. (2014). Penyebab terjadinya Keterlambatan Waktu Penyelesaian Proyek Konstruksi di Dinas PU. Bina Marga Kabupaten Sumenep. Jurnal Ilmiah MITSU, 2(2).
Husen Abrar, 2009, Manajemen Proyek, Edisi Revisi Andi, Yogyakarta
Isnubroto, D., & Putri, C. K. (2021). Analisis Penjadwalan dan Alokasi Sumber Daya pada Proyek Konstruksi Menggunakan Microsoft Project (Studi Kasus Pekerjaan Struktur Proyek XYZ). Wahana Teknik Sipil: Jurnal Pengembangan Teknik Sipil, 26(1), 52-65
Megawati, L. A. (2021). Analisis Faktor Keterlambatan Proyek Konstruksi Bangunan Gedung. Jurnal Teknik| Majalah Ilmiah Fakultas Teknik UNPAK, 21(2).
Purwanto, H. (2016). Kajian Desain Beton Pracetak Sebagai Salah Satu Alternatif Jembatan Bentang Pendek. Jurnal Deformasi, 1(1), 28-42.
S. Arikunto, 2006. Prosedur Penelitian Suatu Pendekatan Praktik. Bumi Aksara, Jakarta
Soeharto,I.,(1999),ManajemenProyek (Dari Konseptual Sampai Operasional) 2. Jakarta : Erlangga
Sulaiman, M., Munirwansyah, M., & Azmeri, A. (2017). Analisis Penyebab Keterlambatan Pelaksanaan Proyek Ditinjau Dari Waktu Pelaksanaan di Provinsi Aceh. Jurnal Teknik Sipil, 1(2), 405-418
Susilowati, S. (2017). Optimasi Waktu Pelaksanaan Pekerjaan Konstruksi dengan Metode Jalur Kritis Menggunakan Software Microsoft Project. Jurnal Teknik Sipil, 8(1).
Telaumbanua, T. A., Mangare, J. B., & Sibi, M. (2017). Perencanaan Waktu Penyelesaian Proyek Toko Modisland Manado dengan Metode CPM. Jurnal Sipil Statik, 5(8).
Walean.D.M., Mandagi,R.J., Tjakra.J., &Malingkas G.Y. (2012). Perencanaan dan Pengendalian Jadwal Dengan Menggunakan Program Microsoft Project 2010 (Studi Kasus Proyek PT Trakindo Utama). Jurnal Sipil Statik. 1(1)
Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2017). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Konstruksia, 6(1).

This work is licensed under a Creative Commons Attribution 4.0 International License.