OPTIMASI PENJADWALAN PROYEK KONSTRUKSI MENGGUNAKAN METODE LEAST COST SCHEDULING

  • Santi Dwi Rahmawati Program Studi Teknik Sipil, UPN “Veteran” Jawa Timur
  • I Nyoman Dita Pahang Putra Universitas Pembangunan Nasional “Veteran”Jawa Timur
  • Anna Rumintang Nauli Universitas Pembangunan Nasional “Veteran”Jawa Timur
Keywords: Direct Cost, Indirect Cost, Least Cost, Project Management

Abstract

Along with the development era, more and more construction projects are built to meet all human needs, ranging from residential homes to business premises or the place of service of the general public. In a project generally have a plan and implementation schedule for the implementation of the project can be run in accordance with the desired plan. Therefore, project management is a strategy that needs to be done in achieving the efficiency and effectiveness of a company. Some of the kinds of methods that can be used to accelerate a construction project can be used to optimize cost and schedule. One of the methods that can be used is the method of Least Cost Analysis. The results of the analysis using the method of least cost scheduling, namely for the duration of the acceleration to be 54 days, 10 days faster than the normal duration. As for the cost of acceleration, i.e. Rp. 3,407,624,263.72 is greater than the normal cost of Rp. 2,856,611,621.08. The difference in the cost of the project acceleration with the normal cost is Rp. 551,012,642.64. Based on efficiency then the project is not worth it to do the acceleration.

References

Adianto, Yohanes L.D., Ali Maliki dan Wisnu Prasetyo.,(2006),Analisis Biaya dan Waktu Optimal pada proyek Ruko Paskal Hypersquare dengan Least Cost Scheduling,14(1).pp.21-29.
Amani, Wahyu., Helmi dan Beni Irawan.,
(2012), Perbandingan Aplikasi Cpm, Pdm, Dan Teknik Bar Chart- Kurva S pada Optimalisasi Penjadwalan Proyek, Buletin Ilmiah Math. Stat. dan Terapannya, 1(1), pp. 15-22.
Abdullah, Rahman., Andi Maddepungeng
dan Azhara Yudha Pradipta.,(2014),
Optimalisasi Waktu dan Biaya dengan Project Crashing dan Tahapan Deterministik Least Cost Scheduling,3(1), pp.46-59.
Ervianto, Wulfram I.,(2004),Manajemen Proyek Konstruksi,Andi, Yogyakarta,pp. 56-135.
Husen, Abrar.,(2010), Manajemen Proyek,Andi, Yogyakarta,pp. 4-187.
Ibrahim, Bachtiar.,(2001), Rencana dan Estimate Real of Cost, Bumi Aksara, Jakarta, pp. 3.
Menteri Tenaga Kerja dan Transmigrasi Republik Indonesia.,(2004) . Jakarta:Nomor KEP. 102/MEN/VI/2004.
Putra, I Nyoman Dita Pahang.,(2019), Framework Of Construction Procedure Manual Of The Project Management Unit And Other Stakeholders In The Surabaya City Government,International Journal of Advanced Research in Engineering and Technology, 10(6), pp. 175
Rangan, Parea Rusan.,(2017),Optimasi Percepatan Durasi Proyek Pembangunan Gedung, Dynamic Saint, (1) pp. 425-442.
Soeharto, Iman.,(1995), Manajemen Proyek (dari Konseptual sampai Operasional), Erlangga, Jakarta, pp. 67-145.
Yomelda, dan Christiono Utomo., (2015), Analisa Earned Value pada Proyek Pembangunan Vimala Hills Villa dan Resort Bogor,Jurnal Teknik ITS, 4(1) pp. 76-81.