ANALISIS PRODUKTIFITAS PENGGUNAAN ALAT BERAT PADA PEKERJAAN TANAH PROYEK JALAN TOL PEKANBARU-BANGKINANG STA 9+300 – 10+000
Keywords:
Heavy equipment, Productivity, Soil Filling Work
Abstract
Pekanbaru-Bangkinang Toll Road uses earthworks. The problem that is happening now is that the land for the entrance, which is at STA 9+350 – 10+000 in the Sungai Pinang area, has just been released in January 2022. In earthworks, there is a target that must be met, which is 2,336,733 m3/day. From the results of the field inspection, it seems that there has been a delay in the earthworks. Therefore, it is necessary to conduct research to determine the cause of the delay. This study focuses on the purpose of knowing the productivity of heavy equipment, in order to determine the solution for the work delays that occur. After conducting a field review, the results of each heavy equipment were 1,727,568 m3/day (excavator), 1,663,230 m3/day (dump truck), 12,344,320 (bulldozer), and 8,300,544 m3/day (vibroroller). From the results obtained, excavators and dump trucks cannot meet the planned targets. So, the handling effort taken is by increasing the number of tools that work in the field. In addition to the addition of tools, the addition of a soil quarry was also carried out, in order to accommodate the additional tools that were carried out. The addition of 6 tools for excavators increased productivity to 3,455,136 m3/day and the addition of 29 dump trucks to 3,455,136 m3/day. Daily volume can be achieved with a record that the performance of the equipment in the field does not decrease and there are no other hindering factors.References
Febrianti, D., & Zulyaden, Z. (2018). Analisis Produktivitas Alat Berat Pada Pekerjaan Timbunan. Jurnal Teknik Sipil Dan Teknologi Konstruksi, 4(1), 21–30. https://doi.org/10.35308/jts-utu.v4i1.586
Ferdinal, L. A. (2019). Perhitungan Produktivitas Alat Berat Pada Pekerjaan Pengurukan Dan Pemadatan Jalan Di Proyek Pembangunan Tol Surabaya Mojokerto. 1–6.
Giarto, R. B., Eng, M., Pongtuluran, E. H., & Eng, M. (2020). Analisa produktivitas alat berat pada pekerjaan timbunan badan jalan pada proyek pembangunan jalan tol balikpapan – samarinda sta 8+865 – 8+925. Jurnal Tugas Akhir Teknik Sipil, 4(1), 1–6. http://ojsmhs.poltekba.ac.id/ojs/index.php/jutateks/article/view/279%0Ahttps://lens.org/056-040-239-783-974
Kaprina, A., Winarto, S., & Purnomo, Y. C. S. (2018). Analisa Produktifitas Alat Berat Pada Proyek Pembangunan Gedung Fakultas Syariah dan Ilmu Hukum IAIN Tulungagung. Jurnal Manajemen Teknologi & Teknik Sipil, 1(1), 1–11. https://doi.org/10.30737/jurmateks.v1i1.136
Kulo, E. N. (2017). Analisa produktivitas alat berat untuk pekerjaan pembangunan jalan (Studi Kasus: Proyek Pembangunan Jalan Lingkar SKPD Tahap 2 Lokasi Kecamatan Tutuyan Bolaang Mongondow Timur). Jurnal Sipil Statik, 5(7), 465–474.
Noptrius. (2021). Analisa Produktivitas Alat Berat Pada Pekerjaan Timbunan Jalan Seberang Taluk-Seberang Benai. 4(1), 12–26.
Sahid, M. N., Listyawan, A. B., Solikhin, M., & Masithoh, S. (2021). Kajian Produktivitas Alat Berat Terhadap Waktu Pelaksanaan Proyek Bendungan Bendo Study of The Productivity of Heavy Equipment to The Implementation Time of The Bendo Dam Produktivitas Alat Berat pada Pembangunan Jalan Ruas Jailolo – Matui Provinsi Maluku. Media Teknik Sipil, 19(1), 33–39.
Setiawati, D. N., & Maddeppungeng, A. (2013). Analisis Produktivitas Alat Berat pada Proyek Pembangunan Pabrik Krakatau Posco Zone IV di Cilegon. Jurnal Konstruksia, 4, 91–103.
Sokop, R. M., Arsjad, T. T., & Malingkas, G. (2018). Analisa Perhitungan Produktivitas Alat Berat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Pekerjaan Pematangan Lahan Perumahan Residence Jordan Sea. Jurnal Tekno, 16(70), 83–88.
Stephanie, S., Lengkong, M., Manoppo, F. J., & Dundu, A. K. T. (2022). Studi Keterlambatan Pelaksanaan Pekerjaan Konstruksi di Kabupaten Minahasa Selatan. 12(1), 49–66.
Studi, L., Simp, J., & Harapan -Kantor Camat Batu Ampar Kabupaten Kutai Timur Faizah Riffat Ma, B. (2021). Analisis Produktivitas Penggunaan Alat Berat Pekerjaan Timbunan Pilihan Pada Pembangunan Jalan. KURVA S : Jurnal Keilmuan Dan Aplikasi Teknik Sipil, 11(1), 293–314. http://ejurnal.untag-smd.ac.id/index.php/TEK/article/view/5116
Utomo, E. M., Wibowo, M. A., & Sriyana, S. (2020). STRATEGI PERCEPATAN PROYEK MENGGUNAKAN METODE CRASH PROGRAM (Studi Kasus : Program Kerja Masa Pengeringan Proyek Rehabilitasi Saluran Induk Klambu Kiri Tahun 2017). Wahana Teknik Sipil: Jurnal Pengembangan Teknik Sipil, 25(2), 166. https://doi.org/10.32497/wahanats.v25i2.2163
Yosieguspa, Y., & Humaeroh, W. (2020). Tinjauan Pelaksanaan Pekerjaan Timbunan Tanah Pada Proyek Pembangunan Lapangan Parkir Jakabaring Sport City Palembang. Jurnal Deformasi, 5(1), 11. https://doi.org/10.31851/deformasi.v5i1.4231
Zurkiyah, Z., & Hidayat, N. (2020). Studi Optimasi Waktu dan Biaya Alat Berat pada Pekerjaan Pondasi dengan Metode Time Cost Trade Off pada Project Pembangunan Terminal LPG Pressurized 4 X 3000 MT Medan-Belawan. Progress in Civil Engineering Journal, 2(1), 1–7.
Ferdinal, L. A. (2019). Perhitungan Produktivitas Alat Berat Pada Pekerjaan Pengurukan Dan Pemadatan Jalan Di Proyek Pembangunan Tol Surabaya Mojokerto. 1–6.
Giarto, R. B., Eng, M., Pongtuluran, E. H., & Eng, M. (2020). Analisa produktivitas alat berat pada pekerjaan timbunan badan jalan pada proyek pembangunan jalan tol balikpapan – samarinda sta 8+865 – 8+925. Jurnal Tugas Akhir Teknik Sipil, 4(1), 1–6. http://ojsmhs.poltekba.ac.id/ojs/index.php/jutateks/article/view/279%0Ahttps://lens.org/056-040-239-783-974
Kaprina, A., Winarto, S., & Purnomo, Y. C. S. (2018). Analisa Produktifitas Alat Berat Pada Proyek Pembangunan Gedung Fakultas Syariah dan Ilmu Hukum IAIN Tulungagung. Jurnal Manajemen Teknologi & Teknik Sipil, 1(1), 1–11. https://doi.org/10.30737/jurmateks.v1i1.136
Kulo, E. N. (2017). Analisa produktivitas alat berat untuk pekerjaan pembangunan jalan (Studi Kasus: Proyek Pembangunan Jalan Lingkar SKPD Tahap 2 Lokasi Kecamatan Tutuyan Bolaang Mongondow Timur). Jurnal Sipil Statik, 5(7), 465–474.
Noptrius. (2021). Analisa Produktivitas Alat Berat Pada Pekerjaan Timbunan Jalan Seberang Taluk-Seberang Benai. 4(1), 12–26.
Sahid, M. N., Listyawan, A. B., Solikhin, M., & Masithoh, S. (2021). Kajian Produktivitas Alat Berat Terhadap Waktu Pelaksanaan Proyek Bendungan Bendo Study of The Productivity of Heavy Equipment to The Implementation Time of The Bendo Dam Produktivitas Alat Berat pada Pembangunan Jalan Ruas Jailolo – Matui Provinsi Maluku. Media Teknik Sipil, 19(1), 33–39.
Setiawati, D. N., & Maddeppungeng, A. (2013). Analisis Produktivitas Alat Berat pada Proyek Pembangunan Pabrik Krakatau Posco Zone IV di Cilegon. Jurnal Konstruksia, 4, 91–103.
Sokop, R. M., Arsjad, T. T., & Malingkas, G. (2018). Analisa Perhitungan Produktivitas Alat Berat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Pekerjaan Pematangan Lahan Perumahan Residence Jordan Sea. Jurnal Tekno, 16(70), 83–88.
Stephanie, S., Lengkong, M., Manoppo, F. J., & Dundu, A. K. T. (2022). Studi Keterlambatan Pelaksanaan Pekerjaan Konstruksi di Kabupaten Minahasa Selatan. 12(1), 49–66.
Studi, L., Simp, J., & Harapan -Kantor Camat Batu Ampar Kabupaten Kutai Timur Faizah Riffat Ma, B. (2021). Analisis Produktivitas Penggunaan Alat Berat Pekerjaan Timbunan Pilihan Pada Pembangunan Jalan. KURVA S : Jurnal Keilmuan Dan Aplikasi Teknik Sipil, 11(1), 293–314. http://ejurnal.untag-smd.ac.id/index.php/TEK/article/view/5116
Utomo, E. M., Wibowo, M. A., & Sriyana, S. (2020). STRATEGI PERCEPATAN PROYEK MENGGUNAKAN METODE CRASH PROGRAM (Studi Kasus : Program Kerja Masa Pengeringan Proyek Rehabilitasi Saluran Induk Klambu Kiri Tahun 2017). Wahana Teknik Sipil: Jurnal Pengembangan Teknik Sipil, 25(2), 166. https://doi.org/10.32497/wahanats.v25i2.2163
Yosieguspa, Y., & Humaeroh, W. (2020). Tinjauan Pelaksanaan Pekerjaan Timbunan Tanah Pada Proyek Pembangunan Lapangan Parkir Jakabaring Sport City Palembang. Jurnal Deformasi, 5(1), 11. https://doi.org/10.31851/deformasi.v5i1.4231
Zurkiyah, Z., & Hidayat, N. (2020). Studi Optimasi Waktu dan Biaya Alat Berat pada Pekerjaan Pondasi dengan Metode Time Cost Trade Off pada Project Pembangunan Terminal LPG Pressurized 4 X 3000 MT Medan-Belawan. Progress in Civil Engineering Journal, 2(1), 1–7.